Skip to Project List

Roadway - Transit Enhancements San Pablo Road (Beach Boulevard to Atlantic Boulevard)

Description

Reconstruction of the existing roadway from a two-lane to a three-lane, divided urban section from Beach Boulevard to Crystal Cove Drive and from Osprey Point Drive to Atlantic Boulevard. These sections will include raised medians, utility improvements, a closed drainage system, bike lanes, sidewalks, and stormwater ponds. From Crystal Cove to Osprey Point Drive, the roadway will be resurfaced with the addition of shoulders, left-turn and right-turn lanes for site access and continuity of the sidewalks. The project involves a complete overhaul of the stormwater collection and conveyance system on the corridor and realignment adding new turn lanes to reduce queuing and improve traffic flow. The design for these improvements is primarily based on addressing safety and drainage improvements.

Project Renderings

001 | 002 | 003 | 004 | 005 | 006

Status

Construction
Project Phase 3B - Final Phase

The contractor is advising that they will complete the project by Mid-December and are escalating work to ensure that all lanes are opened as designed and the project is completed this year. This schedule is very tight and dependent entirely on the contractor and his subcontractors meeting their time commitments. Once the roadway is open in the final traffic pattern some minor touch up operations may continue. Final activation of the new streetlights may also been delayed as the storms affecting Florida this year have had an impact on all electrical work and material supplies. JEA will be activating the new additional streetlights as soon as possible.

Project Phase Construction – Phase 3B

Upcoming Work

Work planned for next week – 11-18-24 through 12-08-24

  • Fine grading for new sidewalk connections and swales.
  • Asphalt placement for final course (nights-3 weeks).
  • Striping for final configuration as asphalt is placed.
  • Median concrete placements-daytime.
  • Remove and replace all median asphalt.
  • Continue new street sign installations.
  • Material removal at JEA Easement area. Ongoing.
  • Curb & sidewalk tie in sections and repairs.
  • Light pole and luminaire installations.
  • Pipe and culvert cleaning.
  • Sod placement.
  • New signal activation and pedestrian signal placements.


NOTES
:

  • Day and nighttime operations are scheduled.
  • Daytime lane shifts will be utilized along with night operations.
  • Traffic will be shifted nightly as new pavement is striping in final traffic plan.

Benefits

The project will reduce traffic congestion and provide safety enhancements for motorists, bicyclists and pedestrians.

Contact

Documents

See More