Roadway - Complete Streets McDuff Avenue - 5th Street (Phase III)

Description

This project will construct drainage improvements and minimal widening from Huron Avenue to Melson Avenue. Work includes asphalt, curb and gutter, sidewalks and closed drainage system.

Status

Construction

Upcoming Work

Work planned for next two weeks – 12-12-22 through 12-23-22

• Fence
• Sanitary Liners/Drops
• Punchlist
• Grading and sodding
• Clean/video new drainage system

*Note - Minor activities may be pursued in additional project area.  No night or weekend work is anticipated.

Benefits

When complete, the area drainage will be improved.