Reconstruct existing roadway to five lanes between Atlantic Boulevard and Ashley Melisse and three lanes between Ashley Melisse and McCormick.  Includes curb and gutter, sidewalks and bike lanes.

Status

Beginning May 14, 2018, Girvin Road will experience its second major roadway traffic shift. Motorist will be placed onto the newly paved sections of Girvin Road from Atlantic Boulevard to Singleton Street. As the project progresses, attention will be given to completing roadway sections along the south side of Girvin Road and all areas north of Singleton Street.

Benefits

The new roadway will increase traffic capacity, decrease congestion and add dedicated bike lanes.

Estimated Schedule

  • Construction Start Date

    March 11, 2016 - September 28, 2018 Construction period
  • Groundbreaking

    March 23, 2016 - March 23, 2016
  • Design Public Meeting

    March 03, 2016 - March 03, 2016 Review of 60 percent design
  • Girvin Road Lane Closure

    October 31, 2016 - November 30, 2016 On Monday, October 31, JTA will be replacing a water main along Girvin Road. The contractor will close the sidewalk on the east side of the road (opposite side of Home Depot) from Atlantic to Ashley Melisse. The west sidewalk will remain open. Pedestrian detours in compliance with FDOT standards will be in place. The work will take place through the end of November.
  • Girvin Road Lane Closures

    August 29, 2016 - September 01, 2016 There may be temporary road closures on northbound Girvin Road between Joeandy and Ashley Melisse after 9:30 a.m. Monday, August 29  through Thursday, September 1 for tree removal. Flaggers will be present to direct traffic and ensure safety of all motorists and pedestrians. Please drive with caution. Note: weather and progress of the crew may alter the closing times.
  • Girvin Road Traffic Shift

    October 18, 2017 - December 31, 2017 A traffic shift will take place at Girvin Road and Singleton Street, shifting traffic from the existing pavement onto our temporary pavement section and will run north ending at Wonderwood Drive.  This shift is anticipated to remain in place through December of 2017.
  • Girvin Road Lane Closure and Detour

    March 05, 2018 - March 09, 2018 A traffic detour will be in placed at Girvin Road near the Atlantic Boulevard Intersection.  JTA will install two (2) storm drain crossings on Girvin Road to support and facilitate drainage as part of the JTA MobilityWorks Grivin Road Project. This work will require a section of Grivin Road to be closed near the intersection of Atlantic Boulevard. A detour will be in place to facilitate traffic through the Girvin Road corridor.
    The detour will occur from 10:00 PM to 5:00 AM starting Monday, March 5, 2018 and ending Friday, March 9, 2018.
     
     
  • Girvan Road Traffic Shift

    May 14, 2018 - July 31, 2018 Effective May 14, 2018, a traffic shift will take place from Atlantic Boulevard to Singleton Street shifting traffic onto the newly paved sections of Girvin Road.